AbTraffo BCTP for BMW AWT Bavaria: Reliable power supply from ABETON

ABETON has successfully implemented another strategically important infrastructure project – the design, manufacture, delivery and installation of the AbTraffo block concrete transformer substation (BCTP) for the BMW AWT Bavaria car dealership in Kyiv.

SEE THE PROJECT

IMPLEMENTATION DESCRIPTION

ABETON has successfully implemented another strategically important infrastructure project – the design, manufacture, delivery and installation of the AbTraffo block concrete transformer substation (BCTP) for the BMW AWT Bavaria car dealership in Kyiv.

 

To ensure a stable and uninterrupted power supply, ABETON designed and implemented a BCTP adapted to the individual needs of the customer. All work – from design to installation – was carried out by highly qualified specialists in compliance with the highest quality and safety standards.

Technical features of the structure:

– Structural basis – monolithic reinforced concrete body with a floor slab, which guarantees the strength and reliability of the structure.

– Waterproofing – the walls are treated with a special sealant that protects against moisture and ensures durability in various climatic conditions.

– Finishing – for harmonious integration into the architectural space, the exterior walls are covered with decorative plaster and painted according to the customer’s request.

– Doors and ventilation – metal doors and ventilation grilles are manufactured and installed in accordance with building regulations for proper air exchange and safety.

 

This project is yet another confirmation of ABETON’s reputation as a reliable manufacturer of integrated reinforced concrete solutions. We continue to work to provide our partners with high-quality, durable and functional infrastructure.

 

ABETON IS A STRONG PARTNER IN CONSTRUCTION!

 

#implementation #ABETON #reinforcedconcrete #construction #BCTP #electricity #transformersubstation #energy #abeton

 

SEE INFORMATION
CONTACT US
info@abeton.ua
IMPLEMENTATION INFORMATION
Time for completion:

2025
Place of implementation:

Kyiv, BMW AWT Bavaria
General contractor:

Grant Energo
Range of services:

Design, production, transportation